[Saratoga Springs News] 2100 North Project Update: 3/4/10
Posted By SSNews on March 4, 2010
The following are planned activities for the coming week. Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.Current Construction Activities
Work on the irrigation system continues just east of Redwood Road. This work will have no impact to traffic. Preparatory work for the future traffic signal at Redwood Road will continue this week. Minor shoulder restrictions remain in place on Redwood Road to ensure the safety of crews in the area. Crews are at work clearing and placing fill in preparation for the future roadway on the west side of the project between the Jordan River and Redwood Road.
Ongoing Project Impacts
In the interest of safety, the small section of Jordan River Trail that falls within the project area has been closed. Access along the trail to the north and south will remain open, but there will be no connecting access through the project during construction.
In order to construct the new railroad bridge and subsequently build the roadway beneath the bridge, UTA and UDOT have fully closed 2100 North between 2300 West and Pointe Meadows Drive. This closure will remain in place through Fall of 2011. Motorists should plan to use 1500 North as an alternate route.